Three months build time at the factory from the date of order.

  1. One week for UAE documentation in Germany once the boat is completed.

  2. One to two weeks for road transport from Wurzburg to Bremerhaven or Hamburg and loading on the ship (which leaves once a week).

  3. Three weeks shipping to Dubai/Jebel Ali  Port.

  4. One to two weeks needed for clearing the Port, registration, commissioning and test sailing prior to handover.

Ex-works equates to: Ready for shipment in the German factory.

NB: This is an approximate guideline only which is not legally binding.